Beulah Apostolic Church
Willesden
Services provided:
Main Contractor
Client:
Chapman & Button Cogress
Construction value:
£3.0 million
Start date:
August 2015
Completion date:
August 2016
Architects:
TMP Architects
Structural Engineers:
Evolve
Mechanical & Electrical:
Irvin Williams
Project managers:
TMP
Build particulars:
New build church – construction of Beulah Apostolic Church
Steel portal frame with concrete & metal decking floor slabs
External envelope comprised of brick & cast stone
Gothic style hardwood windows and entrance & emergency doors
Champion Build completed the core works excluding